Construction Updates

May 2016

Lighting installations are active at various sites.
Sign structure erections are active at various sites.

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
Sandblasting is active at Bridge 15.5.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 16)
Guardrail installations are active at this site.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 17)
Guardrail installations are ongoing at this site.

18th Street/LRT Area (Road Segment 1-Site 18)
Waterproofing for Bridge 18.2 is complete.
Grading at this site is complete.

North Saskatchewan River (Road Segment 2-Site 20)
Bridge 20.1 has been paved.
Construction of the pedestrian bridge at this site is ongoing.
Waterproofing for Bridge 20.2 is complete.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active at this site with transition barriers work.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
The bridge decks have been poured for Bridges 23.1 and 23.5.
Substructure work is active at this site with approach slab construction for the abutments at Bridge 23.3.
Superstructure work is active at this site with barrier construction for Bridge 23.1.
Paving is progressing at this site.
The westbound Yellowhead Trail to southbound Anthony Henday Drive ramp is being widened.
GBC placement is active in several areas of this site.
MSE wall work is ongoing at this site.
Earthworks are ongoing with backfill activities.
Slope work is progressing at this site.
Culvert installations are active at this site.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Yellowhead Trail widening and ditch work is active.
Superstructure work is active at this location with rebar and overhang installation work.
Substructure work is active with wing walls being poured for Bridges 24.1 and 24.2.
Slope work is progressing at this site.
MSE wall backfill earthworks are ongoing.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Substructure work is active with approach and sleeper slab construction for Bridge 25.1.
Substructure formwork is ongoing at this site.
Paving is active at this site.
Curb and gutter work is active at this site.
Catch basin and culvert installations are active at this site.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Substructure work is active in this area with abutment concrete pours.
Superstructure work is active at this location with rebar and overhang installation work.
Girders and deck panels have been installed for Bridge 26.2.
Slope work is progressing at this site.
Culvert installations are active at this site.
Fencing installations are active at this site.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
Substructure work is active with wing walls being poured for Bridge 27.2 and 27.3.
Culvert installations are active at this site.
Fencing installations are active at this site.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Substructure work is active with wing walls being poured for Bridge 28.2.
Widening and ditch cut work is active.
Paving is ongoing at this site.
Culvert installations are active at this site.
Fencing installations are active at this site.
The southbound Anthony Henday Drive to eastbound Baseline Road turn and westbound Baseline Road to southbound Anthony Henday Drive ramp will be opened at the end of the month (weather permitting).

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure work is active at this site with barrier construction for Bridge 29.2.
Paving is ongoing at this site.
Culvert installations are active at this site.
The new southbound Anthony Henday Drive to westbound Sherwood Park Freeway ramp is now open. The mainline traffic has been shifted on to the CD road.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Paving is ongoing at 34 Street and Sherwood Park Freeway. The ramps at 34 Street have been paved.
Paving is ongoing at 17 Street and Sherwood Park Freeway.
Widening work is ongoing at Sherwood Park Freeway at 17 Street.
Substructure work is active with sleeper slab construction.
Curb and gutter work is active at 34 Street at Sherwood Park Freeway.
Guardrail installation is active at this site.

Whitemud Drive/ Anthony Henday drive (Road Segment 4-Site 31)
Reconstruction of the Whitemud Drive has commenced.
Subgrade prep is ongoing on the southbound Anthony Henday Drive to westbound Whitemud Drive and the westbound Whitemud Drive to northbound Anthony Henday Drive loop ramps.
Milling and paving are ongoing on eastbound Whitemud Drive.
Widening and ditch cut work is active at this location.
Culvert installations are active at this site.

 

April 2016

Lighting installations are active throughout the project limits.
Sign structure erections are active throughout the project limits.
Fencing installations are active throughout the project limits.

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
The approach to Bridge 15.5 and the connection to Anthony Henday Drive have been paved.
Guardrail installations are active at this site.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 16)
Paving and sign installation are complete at this site.
Guardrail installations are active at this site.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 17)
Paving and guardrail installations are ongoing at this site.

18th Street/LRT Area (Road Segment 1-Site 18)
Substructure work is active with abutment construction and rebar work for bridge 18.1.

North Saskatchewan River (Road Segment 2-Site 20)
Abutment work is active at bridges 20.1 and 20.2.
Paving activities are ongoing.

Aurum Road/ 130 Ave Area (Road Segment 2-Site 21)
Asphalt work is progressing.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Substructure work is active with approach and sleeper slab construction.
Guardrail installations are active at this site.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Substructure work is active with abutment construction for Bridge 23.4.
Superstructure work is active in this area with barrier forming and rebar work.
Deck pours for Bridge 23.1 are scheduled for early May.
Bridge deck waterproofing is underway for bridges 23.6 and 23.7.
Ramps are being prepared for subgrade, gravel and asphalt.
Backfilling and reinforced fill activities are progressing.
Slope work is progressing at this site.
Culvert installations are active at this site.
The old westbound Yellowhead Trail to southbound Anthony Henday Drive ramp is closed. There is a new traffic intersection at this location.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Substructure work is active with abutment construction for bridges 24.1, 24.2, 24.3 and 24.4.
Deck panels and overhangs are being installed.
Subgrade preparation is ongoing at this site.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Yellowhead Trail widening and ditch cut work is active.
Paving activities are active, resulting in single lane traffic in each direction on Broadmoor Boulevard between Pembina Road and Yellowhead Trail.
Curb and median work is active at Broadmoor Boulevard.
Superstructure formwork is active in this area.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Substructure work in on-going at Bridge 26.2, currently focusing on abutment and pier cap construction.
Girder erections for Bridge 26.2 are scheduled for May 2nd.
The westbound to southbound ramps are being widened.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
The bridge decks have been poured for bridges 27.2 and 27.3.
Culvert and storm sewer installations are active at this site.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Paving activities are ongoing at this site.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure formwork and rebar work is active in this area.
Substructure work is active with abutment construction for bridges 29.2 and 29.3.
Paving activities are in progress at this site.
Northbound Anthony Henday Drive widening and ditch cut work is active.
Reinforced fill activities are progressing.
Culvert installations are active at this site.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Curb and gutter work is active at 34 Street at Sherwood Park Freeway.
MSE Wall work is active at this location.
Topsoil placement and landscaping is in progress.
Paving activities will commence at the beginning of May.

Whitemud Drive/ Anthony Henday drive (Road Segment 4-Site 31)
Earthwork is ongoing at this site.
Reconstruction of the Whitemud Drive will commence in May.

 

Winter 2016

All road work is in hibernation for the winter
Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active throughout the project limits
Culvert and storm sewer installations are active.

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this are with barrier forming and rebar work.

Aurum Road/ 130 Ave Area (Road Segment 2-Site 21)
Superstructure work is active in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge site in this area.
Deck panels and overhangs have been installed on Bridge 23.5.

Yellowhead Trail/ Anthony henday Drive (Road Segment 3-Site 24)
The existing bridges have been demolished for bridges 24.1 & 24.2.
The grider erections have commenced for bridges 24.1 & 24.2.
Superstructure is active at several bridge sites in this area.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with formwork.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
The girder erection has been completed for the remaining two bridges at this location (Bridges 27.2 & 7.3)
Mainline Petroleum Way has been rerouted slightly to the north to allow for the storm sewer to be installed under the road.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Substructure formwork is ongoing at this site.
Earthwork is active in this area (Baseline east)

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Girder erection has been completed for the new Sherwood Park Freeway/ Wye Road Bridge (Bridge 29.2)
Superstructure work is active in this area.
Pond reshaping is underway for pond 29.2.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this locaiton.

Whitemud Drive/ Anthony Henday drive (Road Segment 4-Site 31)
The majority of the culverts were installed throughout this interchange.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
The reconstruciton of mainline Yellowhead Trail is underway.

Fall 2015

*All of the openings below are weather permitting

Sherwood Park Freeway/17 Street Interchange- 17 Street will be reopened with northbound and southbound traffic moved onto the new northbound 17 Street Bridge. All four directional ramps will be opened, and the 76 Avenue temporary connection will be removed. This stage will then remain in place for the remainder of the of the project until the new southbound bridge is completed.

Baseline Road / Anthony Henday Drive Construction - Traffic is now open on two of the three new bridges. There will be further work done to complete the new eastbound and westbound through lanes in order to provide a straight alignment on this section of road. The new eastbound to southbound ramp will be opened. The opening of this new ramp will pull the turning movement traffic out of the eastbound through lanes and provide added capacity for eastbound traffic. The new westbound to northbound ramp will also be opened to commuters.

Sherwood Park Freeway / Wye Road / Anthony Henday Drive- Traffic will be opened over the new Wye Road Bridge, which will allow for the demolition of the existing bridge at this interchange.

Yellowhead Trail(east and west of Northeast Anthony Henday) - Yellowhead Trail will be detoured off the existing lanes and onto the new bridges in the area, to accommodate the demolition of the existing bridges and re-construction of the existing road in the area.

Meridian Street / Hayter Road- Anthony Henday Drive will be extended northbound over the new bridges that cross the CN Rail at Hayter Road and Meridian Street.

Aurum Road - Anthony Henday Drive will be extended northbound to the new interchange at Aurum Road / 130th Avenue.

Broadmoor Boulevard - The completion of Broadmoor Boulevard (south of Yellowhead Trail).

August 2015

Lighting instillations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert and storm sewer instillations are active throughout the project.

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area.
Fencing instillation is active in this area.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active.
Fencing instillation is active in this area.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 17)
Superstructure work is active in this area.
Fencing instillation is active in this area.

18th Street/LRT Area (Road Segment 1-Site 18)
Superstructure work is ongoing in this area.
Earthwork is active at this site.
Surfacing work is progressing at this location.

153 Ave Area (Road Segment 1-Site 19)
The new 153 Avenue and Anthony Henday Drive has been opened to commuters with single lane traffic.
Earthwork activities are ongoing at this location.
Fencing instillation is active at this site.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with barrier forming.

Aurum Road / 130 Ave Area (Road Segment 2-Site 21)
Superstructure work is active in this area.
Surfacing work is active for the new Aurum Road.
Bridge deck waterproofing is underway for Bridge 21.1.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active in this area.
Earthwork is active in this area.
Bridge deck waterproofing is underway for Bridge 22.1.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Earthwork activities continue to elevate Meridian Street to the new permanent alignment.
The girder erection is complete for the new northbound Anthony Henday Drive Bridge over Yellowhead Trail (Bridge 23.1)

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
The new northbound Anthony Henday Drive directional ramp to eastbound Yellowhead Trail was opened to commuters.
Superstructure work is active at several bridge sites in this area.
Bridge deck waterproofing is underway for Bridge 24.3.
Surfacing work is active in this area (Bridge 24.4).

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
The existing westbound Yellowhead to Broadmoor loop ramp bridge in the area was demolished.
Superstructure work is active in this area with formwork.
Earthwork is ongoing at this site.

Anthony Henday Drive/CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with formwork (approach slab/rebar)
Earthwork is active in this area.
Surfacing work is active in this area.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
The mainline traffic of Anthony Henday Drive between Petroleum Way and Sherwood Park Freeway has been rerouted onto the new northbound lanes.
Superstructure work is progressing with formwork.
Earthwork is active at this site.
Surfacing work is active in this area.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
The existing Baseline Road Bridge has been demolished. The new eastbound Baseline Road to northbound Anthony Henday Drive directional ramp will be opened to commuters.
Surfacing work is active in this area.
Substructure formwork is ongoing at this site.
Earthwork is active in this area with topsoil placement.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
The mainline traffic of Anthony Henday Drive between Petroleum Way and Sherwood Park Freeway has been rerouted onto the new northbound lanes.
Superstructure work is active in this area.
Earthwork is active in this area.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Girder have been erected for the new 17 Street Bridge over Sherwood Park Freeway.
Superstructure work is active at this location with deck panel and overhand instillations.
Earthwork is active in this area, which includes the widening of Sherwood Park Freeway.
Surfacing work is active in this area.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Earthwork activities including topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.

 

July 2015

Lighting instillations are active and power distribution centers are being installed.
Sign structure erections are active
Culvert and storm sewer instillations are active throughout the project

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area with concrete pours.
Fencing instillation is active in this area.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active with concrete pours.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 17)
Superstructure work is active in this area.
Surfacing work is ongoing at this site.

18th Street/LRT Area (Road Segment 1-Site 18)
Superstructure work is ongoing in this area.
Earthwork is active at this site
Surfacing work is progressing at this location.

153 Ave Area (Road Segment 1- Site 19)
Earthwork activities are active in this area.
Superstructure work is active for the 153rd Ave Bridge.
Fencing instillation is active at this site.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area for the north approach.
Earthwork is active on the north side of the river with topsoil placement.

130 Ave Area (Road Segment 2-Site 21)
Superstructure work is active in this area.
Surfacing work is active for the new 130th Avenue.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active in this area (transition barriers, sleeper slabs, and approaches)
Earthwork transfer to Site 23 is active in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Earthwork activities continue to elevate Meridian Street to the new alignment.
Deck panel overhangs are being installed (Bridge 23.3)
The girder erection is scheduled for the new northbound Anthony Henday Drive bridge over Yellowhead Trial (Bridge 23.1)

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area.
MSE Wall backfill earthworks is ongoing with 24.9 topsoil placement
Bridge deck waterproofing is underway for Bridge 24.4.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Superstructure work is active in this area.
Earthwork is ongoing at this site.
The service road, north of Yellowhead Trail, is scheduled to be opened

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with formwork.
Earthwork is active in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing with formwork.
Earthwork is active at this site.
Surfacing work is active in this area.
Bridge deck waterproofing is underway work Bridge 27.1.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
The new Baseline Road Bridge over Anthony Henday Drive was opened to traffic (Bridge 28.1)
Surfacing work is active in this area.
The existing north to west ramp was closed in this interchange to put the road on the new alignment.
Substructure formwork is ongoing at this site.
Earthwork is active in this area with topsoil placement

Wye Road/Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure work is active in this area with rebar work (Bridge 29.4), and bridge deck waterproofing (Bridge 29.1)
Northbound Anthony Henday Mainline traffic switch is scheduled.
Earthwork is active in this area.
Surfacing work is ongoing at this interchange.
The existing north to west ramp was closed at this interchange to put the road on the new alignment.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with formwork.
Earthwork is active in this area.
Sherwood Park Freeway widening is active in this area.
Surfacing work is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Earthwork activities including topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.

 

June 2015

Lighting Installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert instillations are active throughout the project.

Manning Drive/Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area with concrete pours (15.7 transition barrier and 15.5 + 15.6 expansion joints)
Fencing instillation is active in this area.

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active with concrete pours (16.1 Curtain Wall)

CN Railroad/Anthony Henday Drive (Road Segment 1-Site 17)
Superstructure work is active in this area.
Surfacing work is ongoing at this site.

18th Street/LRT Area (Road Segment 1-Site 18)
Superstructure work is ongoing in this area.
Earthwork is active in this area.
Surfacing work is active at this site.

153 Ave Area (Road Segment1-Site 19)
Earthwork activities are active in this area.
Superstructure work is active for the new 153rd Ave.
Fencing instillation is active at this site.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with concrete pours for the approach slabs.
Earthwork is active on the north side of the river with topsoil placement.

130 Ave Area (Road Segment 2-Site 21)
Superstructure formwork is active in this area.
Surfacing work is active for the new 130 Avenue.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active in this area with the abutment concrete pours.
Earthwork transfer to Site 23 is active in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Bridge girder erection is complete for the new northbound Anthony Henday Drive to westbound Yellowhead Trail flyover in the area (23.3)
Earthwork activities commence to elevate Meridian Street to the new alignment

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area.
MSE Wall backfill earthworks is ongoing with 24.9 topsoil placement.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Broadmoor Boulevard Bridge over Yellowhead Trail was demolished to make way for the new interchange.
Superstructure work is active in this area with Bridge deck 25.1 ready for rebar.
Girder erection commenced for Bridge 25.2.
Earthwork is active in this area.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with formwork.
Earthwork is active in this area.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing with formwork.
Earthwork is active at this site.
Surfacing work is active for the new northbound Anthony Henday Drive directional ramp to eastbound Yellowhead Trail.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Substructure formwork is ongoing at this site.
Earthwork is active in this area with the new EB-SB Ramp construction, and the new SB-EB loop ramp construction.
The WB-NB ramp is closed to allow for the earthwork fill for the new WB-NB ramp alignment.

Wye Road/Sherwood Park Freeway/Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure work is active in this area.
Northbound Anthony Henday Mainline construction is active with surfacing work.
Earthwork is active in this area.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with formwork.
Earthwork is active in this area.
The southbound 17 Street to westbound Sherwood Park Freeway ramp has been removed to make way for the new interchange.
Sherwood Park Freeway widening is active in this area.
Surfacing work is active in this area.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
The new Sherwood Drive Interchange has been opened to commuters.
Earthwork activities including topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.

May 2015

Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

Manning Drive/ Anthony Henday Drive (Road Segment 1-Site15)
Superstructure work is active in this area with concrete pours and rebar work.
Fencing installation is active in this area.

CN Railroad/ Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active with bridge deck water proofing.

CN Railroad/ Anthony Henday Drive (Road Segment 1-Site 17)
Superstructure work is active in this area with rebar work and concrete pours.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is ongoing with concrete pours.
Earthwork is active in the area.

153 Ave Area (Road Segment 1-Site 19)
Earthwork activities are active in this area.
Superstructure work is active with formwork for transition barrier construction (Bridge 19.1)

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with concrete pours.
Earthwork is active on the north side of the river.

130 Ave Area (Road Segment 2-Site 21)
Superstructure formwork is active in this area.
Fencing instillation is active in this area.

Hayter Road/ CN Railroad Yard Area (Road Segment 3-Site 22)
Superstructure work is active in this area with formwork.
Earthwork stockpiling is active in the area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Bridge installation work continues for the new northbound Anthony Henday Drive to westbound Yellowhead Trail flyover in the area (23.3).
Bridge demolition of the existing Anthony Henday Drive/ Meridian Street Bridge over Yellowhead Trail.
Opening if the new Anthony Henday Drive/ Meridian Street Bridge over Yellowhead Trail.
Earthwork activities commence to elevate Meridian Street to the new alignment.


Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)

Superstructure and substructure work continues at several bridges in this area.
MSE Wall backfill earthworks in ongoing.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Superstructure work continues for the new Broadmoor Boulevard Bridge in this area, with bridge overhang instillations, diaphragm formwork, and concrete pours.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with formwork.
Earthwork is active in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing with formwork.
Earthwork is active in this area.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location is undergoing substructure work with concrete formwork.
Earthwork is active in this area.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.
Northbound Anthony Henday Mainline construction is active.
Earthwork is active in this area.
Fencing instillation is active in this area.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with formwork.
Earthwork is active in this area.
76 Avenue detour is operating.
Bridge demolition of the existing 17 Street Bridge over Sherwood Park Freeway.
Sherwood Park Freeway widening is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.
Earthwork activities including topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.
Paving activities is ongoing in this area.
Fencing and final signage instillation is active in this area.

April 2015

Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

Manning Drive/ Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area with bridge dry finishing and painting.
Bridge 15.5 is undergoing MSE Wall and abutment construction.

CN Railroad/ Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active with transition barrier work.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is ongoing.

153 Ave Area (Road Segment 1-Site 19)
Earthwork activities including backfill and approach slab work.

153 Ave paving activities continues.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with concrete pours and rip rap installation.

130 Ave Area (Road Segment 2-Site 21)
Superstructure formwork is active in this area.
Pond 21 excavation continues.

Hayter Road/ CN Railroad Yard area (Road Segment 3-Site 22)
Superstructure work is active in this area with deck overhang installations.
Earthwork stockpiling in the area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Slope work is progressing at this site and pond shaping is active.
Bridge installation work continues for the new northbound Anthony Henday Drive to westbound Yellowhead Trail flyover in the area (23.3).
MSE Wall construction and ground improvement (Bridge 23.3)
Pond excavation and earthwork haul continues in the area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area, with rebar work, overhand installations and approach slab construction.
MSE Wall backfill earthworks is ongoing.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Superstructure work continues for the new Broadmoor Boulevard Bridge in this area, with formwork ad concrete pours.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with rebar work and concrete pours.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location is undergoing substructure work with concrete formwork and overhang installations.
Topsoil placement is active for the northbound to eastbound ramp and the westbound to northbound ramp at this location.
Bridge 28.1 is undergoing bridge water proofing work.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.
Pond channel construction is underway with Pond 29.2.
Northbound Anthony Henday Mainline construction is active.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with rebar and overhang installation work.
Earthwork stripping is beginning in this area.
76 Avenue detour construction is continuing.
Sherwood Park Freeway widening is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.
Earthwork activities including topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.

March 2015

Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

Manning Drive/ Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area with concrete pours and rebar work.

CN Railroad/ Anthony Henday Drive (Road Segment 1 - Site 16)
Superstructure formwork is active with concrete pours and rebar work.

18th Street/ LRT Area (Road Segment 1- Site 18)
Superstructure formwork is ongoing.

153 Ave Area (Road Segment 1 - Site 19)
Earthwork activities including backfill and approach slab work.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with deck panel erections and overhand installations.
Earthwork activities including headslope construction.
Wing wall concrete pours are active.

130 Ave Area (Road Segment 2-Site 21)
Superstructure formwork is active in this area.

Hayter Road/ CN Railroad Yard area (Road Segment 3-Site 22)
Superstructure work is active in this area with deck overhang installations.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site23)
Superstructure formwork is active at several bridge sites in this area.
Substructure concrete pours for piers for bridge 23.3.
Slope work is progressing at this site and pond shaping is active.
Bridge installation work has commenced for the new northbound Anthony Henday Drive to westbound flyover in the area (23.3).
Pond excavation and earthwork haul has commenced.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area.
Ground thaw work is active.
MSE Wall backfill earthworks is ongoing.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Superstructure work continues for the new Broadmoor Boulevard Bridge in this area, with formwork and concrete pours.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area with rebar work and concrete pours.
GBC Stockpiling has commenced in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location is ongoing substructure work. With concrete formwork and overhang installations.
Topsoil placement is active for the northbound to eastbound ramp at this location.
Bridge 28.1 is undergoing bridge dry finishing work.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.
Pond work topsoil placement is active (Pond 29.1 + 29.2)
Wing wall installation is active for bridge 29.1.
Bridge 29.4 is undergoing bridge diaphragm work and overhand installations.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with rebar and overhang installation work.
Earthwork stripping is beginning in this area.
76 Avenue detour construction is commencing.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.
Topsoil placement is active.
Yellowhead Trail widening and ditch cut work is active.

February 2015

All road work is in hibernation for the winter.
Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

Manning Drive/ Anthony Henday Drive (Road Segment 1-Site 15)
Superstructure work is active in this area with concrete pours and rebar work.

CN Railroad/ Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active with concrete pours and rebar work.

18th Street/ LRT Area (Road Segment 1- Site 18)
Superstructure formwork is ongoing.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with deck panel erections and overhang installations.

130th Ave Area (Road Segment 2-Site 21)
Superstructure formwork is active in this area.

Hayter Road/ CN Railroad Yard area (Road Segment 3-Site 22)
Superstructure work is active in this area with deck overhang installations.
Slope work is progressing at this site.

Yellowhead Trail/ Anthony Henday Drive (Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Slope work is progressing at this site and pond shaping is active.
Watermain installation work is active at this location.
Bridge installation work is scheduled to commence for the new northbound Anthony Henday Drive to westbound flyover in the area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Superstructure work continues for the new Broadmoor Boulevard Bridge in this area, with soffit installation, formwork, and concrete pours.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Superstructure work is active in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing in this area with concrete pours

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location is ongoing substructure work.
Girder erection is complete for the new westbound to southbound loop ramp (Bridge 28.2)

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.
Girder erection is complete for the new eastbound to northbound directional ramp (Bridge 29.4)

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Superstructure work is active at this location with rebar work.
Girder erection is complete for the new northbound bridge at this interchange (Bridge 30.1)
Watermain and sanitary like installation work is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.
MSE weeping tile work is progressing at this site.

January 2015

All road work is in hibernation for the winter.
Lighting installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

CN Railroad/ Anthony Henday Drive (Road Segment 1-Site 16)
Superstructure formwork is active.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is ongoing.

North Saskatchewan River (Road Segment 2-Site 20)
Superstructure work is active in this area with deck panel and overhang installations.

130th Ave Area (Road Segment 2-Site 21)
Superstructure work is active in this area.
MSE weeping tile work is ongoing.
Pond 21 MSE sand mining is progressing.

Hayter Road/ CN Railroad Yard Area (Road Segment 3-Site 22)
Substructure and Superstructure work is active in this area.
Slope work is progressing at this site.

Yellowhead Trail/ Anthony Henday Drive (Segment 3-Site 23)
Superstructure formwork is active at several bridge sites in this area.
Slope work is progressing at this site.
Watermain installation work is active at this location.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
Superstructure and substructure work continues at several bridges in this area.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Substructure work continues for the new Broadmoor Boulevard Bridge in this area.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Substructure work is active in this area.
Topsoil placement for south service road in the area is active.

Anthony Hendy Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing in this area.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location is ongoing substructure work.
Girder erection is scheduled for early February for the new westbound to southbound loop ramp (Bridge 28.2).
Topsoil removal from pond 28-1 is active.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.
Girder erection is scheduled for one of the bridges for the new eastbound to northbound directional ramp (Bridge 29.4).

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Substructure work is active at this location.
Girder erection is scheduled to take place in mid-February for the new northbound bridge at this interchange (Bridge 30.1).
Watermain and Sanitary line installation work is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.
MSE weeping tile work is progressing at this site.

November / December 2014

Project Wide
All road work is in hibernation for the winter.
Lighting Installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is on-going

North Saskatchewan River (Road Segment 1-Site 20)
Superstructure work is active in this area.

130th Ave Area (Road Segment 2-Site 21)
Superstructure work is active in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Substructure and Superstructure work is active in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
Retaining wall work continues.
Superstructure and substructure work continues at several bridges in this area.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Watermain work is active in this area.
Substructure work continues for the new Broadmoor Boulevard Bridge in this area.

Anthony Henday Drive/CP Railroad Area (Road Segment 3-Site 26)
Substructure work is active in this area.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing in this area.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location has ongoing substructure work.

Wye Road/Sherwood Park Freeway/Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and substructure work is active in this area.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 31)
Substructure work is active at this location.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Superstructure work is active in this area.

October 2014

Project Wide
Lighting Installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is on-going.

153rd Ave Area (Road Segment 1-Site 19)
Paving of 153rd Ave is progressing (to be shut down early November).

North Saskatchewan River (Road Segment 1-Site 20)
Retaining wall construction continues.
The river berm removal is progressing.

130th Ave Area (Road Segment 2-Site 21)
Stormline installation work is active in this area.
Paving of 130th Ave is progressing (to be shut down early November).

Hayter Road/ CN Railroad Yard Area (Road Segment 3-Site 22)
Girders are being erected on the new bridge going over the CN Rail in the area.
Substructure work is active in this area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure and substructure work are active at several bridges in this area.
Storm sewer work is active.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
MSE Wall work continues in this area.
Retaining wall work continues.
Superstructure and substructure work continues at several bridges in this area.
Backfilling and Reinforced Fill activities are progressing.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Watermain work is active in this area.
The south service road at this location is scheduled to be paved.

Anthony Henday Drive/ CP Railroad Area (Road Segment 3-Site 26)
Substructure work is active in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work is progressing in this area.
Northbound mainline paving is progressing.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
The second bridge at this location has ongoing substructure work.
Northbound mainline paving is progressing.
Watermain work is active at this location.
Curb and gutter work is active at this location.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and Substructure work is active in this area.
Paving activities for northbound mainline is progressing.
Stormline work is active in this area.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 31)
Substructure work is active at this location.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Road approaches are complete and sidewalks are being prepped.
Curb and gutter work is active.
Paving is progressing in this area.
Minor signs and guardrail are being installed.

 

September 2014

Project Wide
Lighting Installations are active and power distribution centers are being installed.
Sign structure erections are active.
Culvert installations are active throughout the project.

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Road work activities continue with road paving at several ramps and loops, followed by the mainline.
MSE Wall work is active at this location.
Storm line installation work is active in this area.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is on-going.
The bridge deck at this location is scheduled to be poured.

153rd Ave Area (Road Segment 1-Site 19)
Paving of 153rd Ave is scheduled.

North Saskatchewan River (Road Segment 1-Site 20)
Retaining wall construction continues.
The river berm is scheduled to be removed.

130th Ave Area (Road Segment 2-Site 21)
Stormline installation work is active in this area.
Paving of 130th Ave is scheduled.

Hayter Road/ CN Railroad Yard Area (Road Segment 3-Site 22)
Shoring is being removed.
Substructure work is nearing completion.
Reinforced Fills are active.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure and substructure work are active at several bridges in this area.
Bridge deck waterproofing is scheduled.
Hayter Road is scheduled to be paved before the winter.
Storm sewer work is active.
MSE Walls, Reinforced Fills and Retaining Walls are being built at several locations.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)

MSE Wall work continues in this area.
Retaining wall work continues
Superstructure and substructure work continues at several bridges in this area.
Backfilling and Reinforced Fill activities are commencing.

Broadmoor Boulevard/ Yellowhead Trail (Road Segment 3-Site 25)
Watermain work is active in this area.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work has begun in this area.
Northbound mainline paving is progressing.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
Bridge waterproofing is scheduled this fall.
The second bridge at this location has ongoing substructure work.
Watermain work is active at this location.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Superstructure and Substructure work is active in this area.
Paving activities for northbound mainline is progressing.
Stormline work is active in this area.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Road approaches are complete and sidewalks are being prepped.
Curb and gutter work is active.
Paving is progressing in this area.
Minor signs and guardrail will be installed this fall.

August 2014

Project Wide
Lighting installation is active and power distribution centers are being installed.
Sign structure erections are active.

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Road work activities continue with road paving at several ramps and loops, followed by the mainline.

CN Railroad and Anthony Henday Drive (Road Segment 1-Site 16)
Road work activities continue with paving.
Storm Sewer work has commenced.

18th Street/ LRT Area (Road Segment 1-Site 18)
Superstructure formwork is on-going.
Road work activities continue, with road paving, and curb and gutter work to follow.
Sign installation has commenced in this area.

153rd Ave Area (Road Segment 1-Site 19)
Deck is schedule to be cast.
Stormline is being installed.
Paving of 153rd Ave will commence this fall.

North Saskatchewan River (Road Segment 1-Site 20)
Retaining wall construction continues.
The pedestrian walking panels are being erected.
Road work is active with paving activities continue south of the river.
Drainage outfall construction activities are active.
The river berm will be removed in September / October.

130th Ave Area (Road Segment 2-Site 21)
Curb and gutter work is commencing in this area this fall.

Hayter Road/ CN Railroad Yard Area (Road Segment 3- Site 22)
Shoring is being removed.
Substructure work continues in the area.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure and substructure work at active at several bridges in this area.
Storm sewer work is active.
MSE Walls are being built at several locations.

Yellowhead Trail/ Anthony Henday Drive (Road Segment 3-Site 24)
MSE Wall work continues in this area.
Retaining wall work continues.
Superstructure work continues at several bridges in this area, and backfilling activities are starting.
Reinforced fill are commencing.

CN Rail Yard/ Yellowhead Trail (Road Segment 3-Site 26)
Substructure work is complete and girders are being erected.
Superstructure work is starting.

Anthony Henday Drive/ Petroleum Way (Road Segment 3-Site 27)
Superstructure work has begun in this area.
Drainage work is active.
Northbound mainline paving will commence in this area this fall.

Baseline Road/ Anthony Henday Drive (Road Segment 4-Site 28)
Bridge backfilling is nearly complete in this area.
Paving activities will start on the northbound mainline this fall.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 2-Site 29)
The first bridge deck has a few more elements to be cast before backfilling can commence, and the second bridge deck will me poured shortly.
Paving activities will commence on the northbound mainline this fall.

Whitemud Drive/ Anthony Henday Drive (Road Segment 4-Site 31)
Paving of the eastbound-southbound ramp will occur this fall.

Sherwood Drive/ Yellowhead Trail (Road Segment 5-Site 32)
Road approaches continue to be built, and bridge approach work is complete.
Curb and gutter work will commence shortly.
High mast poles will be erected this fall.
Paving will commence in this area this fall.

June / July 2014

Project Wide
Utility Protective Slabs are being constructed.
Lighting installation is active.
Sign structures are arriving on site.

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Superstructure formwork os on-going and decks are being poured.
Road work activities continue with road paving and light pole installations.

CN Railroad and Anthony Henday Drive (Road Segment 1-Site 16)
Road work activities continue with paving.
Storm sewer work has commenced.
Sign installation work has begun.

18th Street/LRT Area (Road Segment 1-Site 18)
Superstructure formwork is on-going, and the bridge deck is ready to be poured.
Road wok activities continue, with road paving, and curb and gutter work to follow. Sign installation has commenced.

153rd Ave Area (Road Segment 1-Site 19)
Substructure and wall formwork is continuing. Deck will be cast, followed by barrier casting.
Curb and gutter work has commenced.

North Saskatchewan River (Road Segment 1-Site 20)
Retaining wall construction continues.
Girders are being set on the north span, followed by the pedestrian walking panels.
Road work is active with paving commencing in the area.

130 Ave area (Road Segment 2-Site 21)
Culvert construction continues.
Road work activities continue in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Road work activities have commenced in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Superstructure work and Piling activities are active at several bridges in this area.
Storm sewer work is active.
Retaining wall work has begun.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
Road work and Culvert Installation work is active in this area.
MSE Wall work continues in this area.
Retaining wall work continues.
Superstructure work continues at several bridges in this area.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Culvert work is active in this area.

CN Rail Yard/Yellowhead Trail (Road Segment 3-Site 26)
MSE Wall construction is complete in this area.
Substructure work has begun.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
MSE Wall work has commenced.
Pile driving activities and substructure work has begun in this area.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Barrier work continues on the wide bridge.
The second bridge deck is being poured.
High mast work has commenced at this location.
Road work and culvert work is active in this area.

Wye Road/Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4-Site 29)
Stage 1 of the MSE Wall construction is complete.
The first bridge deck at this location has been poured and the second bridge deck will be poured shortly.
Sherwood Park freeway has been paved.

Sherwood Park Freeway/17 Street (Road Segment4-Site 30)
The northbound eastbound ramp is being rebuilt on the 17 Street bridge.
MSE Wall work has commenced.
Roadwork continues with ramp paving.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
MSE Wall work is active at this location
Road approaches continue to be built, and bridge approach work has begun.
Storm Sewer and Roadwork is active.

April / May 2014

Project Wide
Utility Protective Slabs are being constructed and installed.
Utility relocations continue

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Superstructure formwork is on-going.
Girders are set and deck work can start for two bridges in the Manning Drive Interchange.
The deck has been cast and barrier work will follow for 3rd bridge.
Road work activities have commenced.

CN Railroad and Anthony Henday Drive (Road Segment 1-Site 16)
Road work activities have commenced.

18th Street/LRT Area (Road Segment 1-Site 18)
Substructure formwork is on-going.
Road work activities have commenced.
Girders have been set, superstructure work can commence at this location.

153rd Ave Area (Road Segment 1-Site 19)
Superstructure formwork is continuing. Deck will be cast, followed by barrier casting.
Traffic signal work continues.

North Saskatchewan River (Road Segment 1-Site 20)
Pier work continues.
Retaining wall construction continues.
Piling is occurring on the north slope.
Girders to be set on the mid bridge span.

130 Ave area (Road Segment 2-Site 21)
Superstructure work is active in the area.
Culvert construction continues.
Road work activities have commenced in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Road work activities have commenced in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Substructure work and Piling activities are active in this area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
Road work and Culvert Installation work is active in this area.
MSE Wall work has commenced in this area.
A bridge deck has been cast, and a second bridge deck will be cast shortly.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Culvert work is active in this area.

CN Rail Yard/ Yellowhead Trail (Road Segment 3-Site 26)
MSE Wall construction has commenced.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Culvert work is active at this location.
Approaches to the bridge are being built.
The Sherwood Drive Bridge deck has been cast, and the barriers and approaches are beginning.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
High mast work continues at this location.
Culvert installation work is active in this area.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
A bridge deck has been cast and barrier work has begun.
A second bridge deck is being formed.
High mast work has commenced at this location.

Wye Road/Sherwood Park Freeway/Anthony Henday Drive (Road Segment 4-Site 29)
MSE Wall construction and Culvert Installation work has begun.
The first bridge deck at this location is being formed to be poured shortly.
Sherwood Park Freeway will be milled and paved shortly.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
The Northbound eastbound ramp is being rebuilt on the 17 St bridge.
MSE wall work will commence shortly.

 

March 2014

Project Wide
Culvert Installation is on-going.
Utility Protective Slabs are being constructed and installed.
Utility relocations continue.

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Substructure and superstructure formwork is on-going.

CN Railroad Area (Road Segment 1-Site 17)
Superstructure formwork is continuing.

18th Street/LRT Area (Road Segment 1-Site 18)
Substructure formwork is on-going.
Shaw/EPCOR/TELUS Utility work will continue through to the beginning of April.
Setting girders will commence at this location.

153rd Ave Area (Road Segment 1-Site 19)
EPCOR line relocation is wrapping up.
Superstructure formwork is continuing.
Traffic signal work has commenced.

North Saskatchewan River (Road Segment 1-Site 20)
Substructure work is continuing.

130Ave Area (Road Segment 2-Site 21)
Superstructure work is active in the area.
Culvert construction has begun.
Sign foundation work has commenced.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Watermain work is active.
Substructure formwork continues in the area.
MSE Wall construction has commenced.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23)
Storm Waterline is being installed in this area.
AltaLink connection work is on-going in this area.
MSE Wall construction has begun.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
Topsoil stripping activities are beginning at this location.
Storm Waterline is being installed in this area.
Girders will begin to be erected for Bridges 23.4 & 24.4.
Substructure work continues.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Sign structure foundation work is continuing.

Anthony Henday Drive/Petroleum Way (Road Segment 3-Site 27)
Sign foundation work has commenced at this location.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Superstructure work is on-going.
Construction has begun on the new northbound to eastbound ramp.

Wye Road/ Sherwood Park Freeway/Anthony Henday Drive (Road Segment 4-Site 29)
Substructure and Superstructure work continues.
Pipeline utility relocation work continues.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Substructure work continues.
Storm Waterline is being installed at this location

 

February 2014

Project Wide
All road work is in hibernation for the winter
Culvert Installation is ongoing.
Utility Protective slabs are being constructed and installed.
Utility relocations are underway.

Manning Drive and Anthony Henday Drive Interchange (Road Segment 1-Site 15 &16)
Substructure and superstructure formwork is on-going.

CN Railroad Area (Road Segment 1-Site 17)
Superstructure formwork is continuing.

18th Street/LRT Area (Road Segment 1-Site 18)
Substructure formwork is on-going.
Shaw/EPCOR/TELUS Utility work will continue through to the beginning of April.

153rd Ave Area (Road Segment 1-Site 19)
Sewer line is being relocated.
EPCOR line relocation will be complete at the end of March.
Superstructure formwork is continuing.

North Saskatchewan River (Road Segment 1- Site 20)
North berm foundation work has commenced.
Substructure work is continuing.

130Ave Area (Road Segment 2-Site 21)
Superstructure work is active in the area.

Hayter Road/CN Railroad Yard Area (Road Segment 3- Site 22)
Watermain work is active.
Substructure work is active in the area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 24)
EPCOR Utility work will continue into mid-April.
Pipeline Utility work will commence in March in this area.

Broadmoor Boulevard/Yellowhead Trail (Road Segment 3-Site 25)
Foundation work will commence mid-March.
Pipeline and EPCOR Utility work will continue in this area.
Sign structure foundation work is continuing.

Anthony Henday Drive/CN Railroad (Road Segment 3-Site 26)
Foundation work at this location will be complete at the end of March.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Superstructure work is on-going

Wye Road/Sherwood Park Freeway/Anthony Henday Drive (Road Segment 4-Site 29)
Substructure work continues.
Superstructure work has begun.
Girders have been erected for the Eastbound/Northbound ramp.
Fortis and Pipeline Utility relocation work continues through the beginning of March.

Sherwood Park Freeway/ 17 Street (Road Segment 4-Site 30)
Foundation work at this location is complete.
Substructure work has commenced in this area.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Girders have been erected for the new Sherwood Drive Bridge over Yellowhead Trail.
Sign structure foundation work is continuing in this area.

December 2013/January 2014

Project Wide
All road work is in hibernation for the winter.
Culvert Installation is ongoing.
Utility Protective slabs are being constructed and installed.
Utility relocations are underway.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Sign Structure and High Mast foundation work will begin in January.
Substructure and superstructure formwork is on-going.

18th Street/LRT Area (Road Segment 1-Site18)
Substructure formwork is ongoing.

153rd Ave Area (Road Segment 1-Site 19)
Sever line is being relocated.
EPCOR line is being fused and tested and commissioned in January.

North Saskatchewan River (Road Segment 1-Site 20)
Pedestrian substructure is ongoing.
South berm removal activities are complete.
North berm construction is ongoing.

130 Ave Area (Road Segment 2-Site 21)
Deck Panels will be placed in Mid-January.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Watermain work is active.
Substructure work is active in the area.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23 & 24)
Substructure work is active in the area.
Foundation work is ongoing.

Anthony Henday Drive/CN Railroad (Road Segment 3-Site 26)
Foundation work at this location will be complete Mid-January.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Deck formwork is ongoing.

Wye Road/ Sherwood Park Freeway/ Anthony Henday Drive (Road Segment 4- Site 29)
Substructure work continues.
Waterline Installation will be complete in January.

Sherwood Park Freeway/ 17 Street (Road Segment 4- Site 30)
Foundation work at this location is ongoing.

Off Site
Concrete girders, steel girders, and deck panels are being fabricated.
MSE Wall panels, expansion joints, and bridge bearings are being fabricated.

October/November 2013

All road work is in hibernation for the winter.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Light pole foundation work will start in November.
Substructure and superstructure formwork is on-going.
Girders to be set at Bridge 15.5 (late November)

CN Railroad Area (Road Segment 1- Site 17)
Deck formwork is rebar installation is on-going

18th Street/LRT Area (Road Segment 1-Site 18)
Substructure formwork is ongoing.

153rd Ave Area (Road Segment 1-Site 19)
Superstructure formwork continues.
Sanitary line work is to commence in December.

North Saskatchewan River (Road Segment 1-Site 20)
Pedestrian substructure is on-going.
South berm removal activities have begun.
North berm construction has begun.

130 Ave Area (Road Segment 2-Site 21)
Waterline is being installed.
Girder erection will occur in November.
Pipeline relocation work in ongoing in the area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Pile driving and reinforced fill activities are complete.
Watermain work is active.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23 & 24)
Substructure work is active in the area.

Anthony Henday Drive/CN Railroad (Road Segment 3-Site 26)
Foundation work is on-going at this location.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
Deck formwork is on-going.
Culvert Installation work continues in this area.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drive (Road Segment 4-Site 29)
Substructure work continues.
Superstructure work has commenced.
Waterline installation continues.
Pond work is active.
Culvert work continues in the area.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Substructure work is active in this area.

Off Site
Concrete girders, steel girders, and deck panels are being fabricated.
MSE Wall panels and bridge bearings are being fabricated.
Utilities- Project wide pipeline and utility relocations are underway.

September 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Light pole foundation work will start in October
Bridge 15.6 MSE Wall construction has commenced.
Placing gravel on Mainline Roadway and paving in October.
Site 16 Watermain connection is complete.
Site 16 girders are set.
Substructure and superstructure formwork is on-going.

CN Railroad Area (Road Segment 1-Site 17)
Substructure work and girder erection is complete.
Deck form work and rebar installation is on-going.
Roadwork activities continue.

18th Street/LRT Area (Road Segment 1-Site 18)
Subsructure formwork has started.
Roadwork activities continue.

153rd Ave Area (Road Segment 1-Site 19)
Supersructure formwork has started.
Stormline work is active.
Roadwork activities are continuing.
Sanitary line work will start in October.

Mainline Anthony Henday Drive (Between Yellowhead Trail and Sherwood Park Freeway)
Drainage work is active on the new northbound Anthony Henday Drive.
Paving activities will commence in October.

North Saskatchewan River (Road Segment 1-Site 20)
Southside girder erection will be complete in October.
Pedestrian substructure is on-going.
South berm removal activities have begun.
North berm construction has begun.
Pond outfall construction is finishing.
Earthwork activities continue in this area.

130 Ave Area (Road Segment 2-Site 21)
Road work is on-going in this area.
Substructure formwork has commenced.
Waterline is being installed.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Road work is continuing for the new Meridian Street.
Pile Driving is continuing.
Reinforced fill activities have begun.
Drainage work is active.
CP track realignment and MSE Wall work will commence in October.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3-Site 23 & 24)
Drainage and substructure work is active in this area.
Detour is being paved in October.
Road fill continues.
Reinforced fill activities will commence in October.

Broadmoor/Yellowhead Trail (Road Segment 3- Site 25)
Road fill is on-going in this area.

Anthony Henday Drive/ CN Railroad (Road Segment 3-Site 26)
Foundation work is on-going at this location.


Baseline Road/ Anthony Henday Drive (Road Segment 4- Site 28)
Beck formwork is on-going.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drie (Road Segment 4-Site 29)
High mast foundation work is on-going.
Girder erection will commence over the Henday in October.
MSE Wall and substructure work continues in this area.
Waterline is being installed.
Pond work is active.
Bridge culvert work is on-going.

Sherwood Park Freeway/17 Sreet (Road Segment 4-Site 30)
High mast foundation work is on-going.

Sherwood Drive/Yellowhead Trail (Road Segment 5- Site 32)
Sanitation line work is on-going at this location.
Road fill continues in this area.
Pier formwork is active.
High mast foundation work continues.

Off Site
Concrete girders, steel girders, and deck panels are being fabricated.
MSE Wall panels and bridge bearings are being fabricated.
Utilities- Project wide pipeline and utility relocations are underway.

August 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Bridge 15.6 MSE Wall construction is scheduled to start in September.
Placing gravel on Mainline Roadway.
Site 16 Watermain work continues.
Site 16 girders will be set mid-September.
Deck formwork to follow after girder erection.

CN Railroad Area (Road Segment 1-Site 17)
Substructure work is complete.
Girders will be set mid-September.
Deck form work will follow after girder erection.

18th Street/LRT Area (Road Segment 1-Site 18)
MSE Wall construction continues.
Storm-line work is progressing.

153rd Ave Area (Road Segment 1-Site 19)
Deck panels are being erected.
Deck formwork has started.
Roadwork and Drainage activities continue in this area.
Curb and gutter work to begin at the end of September.

Mainline Anthony Henday Drive (Between Yellowhead Trail and Sherwood Park Freeway)
Detour work is complete.
Drainage work is active on the new northbound Anthony Henday Drive.
Milling operations continue on the old northbound Anthony Henday.

North Saskatchewan River (Road Segment 1-Site 20)
Girder erection and substructure work is on-going.
Earthwork activities continue in this area.

130 Ave Area (Road Segment 2-Site 21)
Road work is on-going in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Road work is continuing for the new Meridian Street.
Utilities- Pembina Pipeline relocation work is continuing.
Pile Driving in this area to begin at the end of September.
Drainage work is active.

Yellowhead Trail/Anthony Henday Drive (Road Segment 3- Site 23 & 24)
Drainage work, Substructure work, and Pond work is active in this area.
Preload activities have started for abutments.
Waterline is being installed.
Road fill continues.
MSE work has begun at Site 24.

Broadmoor/Yellowhead Trail (Road Segment 3-Site 25)
Road fill is on-going in this area.

Anthony Henday Drive/CN Railroad (Road Segment 3-Site 26)
Drilled shafts work is on-going at this location.

Baseline Road/Anthony Henday Drive (Road Segment 4-Site 28)
MSE Wall construction is complete.
Substructure work is complete.
Girders will be set at the end of September.
Deck formwork will commence after girder erection is complete.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drive (Road Segment 4-Site 29)
Pipe Driving operations are complete.
MSE Wall and substructure work continues in this area.
Storm-line is being installed.

Sherwood Park Freeway/17 Street (Road Segment 4-Site 30)
Bridge Culvert to be installed at the end of September.

Sherwood Drive/Yellowhead Trail (Road Segment 5-Site 32)
Drainage work is active.
Storm sewer and sanitation line relocation work is on-going at this location.
Road fill and Pile Driving operation continue in this area.

Off Site
Concrete girders, steel girders and deck panels are being fabricated.
MSE Wall panels and Bridge bearings are being fabricated.
Utilities-Project wide pipeline and utility relocations are underway.

July 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 &16)
Bridge 15.7 girders and deck panels have been erected. Preparing for deck pour.
Bridge 15.6 MSE Wall construction is scheduled to start at the end of August.
Drainage work is complete Mainline Roadway is ready for gravel, and asphalt.
Ramps are being prepared for subgrade, gravel and asphalt.
Site 16- MSE Wall construction is complete.
Site 16- Watermane work will finish in August.

CN Railroad Area (Road Segment 1-Site 17)
MSE Wall construction is complete.
Substructure work has commenced.
Roadway will work has begun.

18th Street/LRT Area (Road Segment 1-Site 18)
MSE Wall construction will start in August.
Utilities-Pembina Pipeline relocation work is on-going.
Roadway fill work has begun.

153rd Ave Area (Road Segment 1-Site 19)
Girder erection at this location is complete.
Deck panels are to be erected in August.
Drainage work is on-going.
Utilities-Pembina Pipeline relocation work is on-going in this area.

Mainline Anthony Henday Drive (Between Yellowhead Trail and Sherwood Park Freeway)
Detour work will be complete in August.

North Saskatchewan River (Road Segment 2-Site 20)
Girder erection has commenced at this location.
Substructure work is on-going (at piers and abutments).
Earthwork activities are on-going in this area.

130 Ave Area (Road Segment 2-Site 21)
MSE Wall construction is on-going.
Roadwork is on-going in this area.

Hayter Road/CN Railroad Yard Area (Road Segment 3-Site 22)
Road fill is on-going for the new Meridian Street.
Utilities- Pembina Pipeline relocation work is continuing.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3- Site 23 & 24)
Substructure work is active at these sites.
Pile driving operations will begin in August at Site 23.
Pond work is on-going in this area.
ATCO Pipeline relocation work in on-going in this area.

Anthony Henday Drive & CN Railroad (Road Segment 3-Site 26)
Drill shaft work is on-going at this location.
Pond work will commence at this location in August.
Preparation work for substructure work has commenced at this location.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
MSE Wall construction will commence in August.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drive Area (Road Segment 4-Site 29)
Pile driving operations will be on-going at this location.
Storm sewer relocation work in on-going in this area.
ATCO Pipeline relocation work in on-going in this area.

Sherwood Drive & Yellowhead Trail (Road Segment 5-Site 32)
Storm sewer and sanitation line relocation work is on-going at this location.

Off Site
Concrete girders are being fabricated.
Deck panels are being fabricated.
Steel girders are being fabricated.
MSE Wall panels are being fabricated.
Bridge bearings are being fabricated.

June 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Bridge 15.7 interchange superstructure work to begin in July.
Drainage and Earthworks are on-going in this area.
Site 16- MSE Wall construction on-going.
Utilities- EPCOR line relocation work in Site 16.

CN Railroad Area (Road Segment 1- Site 17)
MSE Wall construction is on-going.
Drainage work is on-going.

18th Street / LRT Area (Road Segment 1- Site 18)
Utilities- Pembina and ATCO Pipeline relocation work is on-going.
Utilities- EPCOR power line relocation work is on-going.

153rd Ave Area (Road Segment 1- Site 19)
Girder erection at this location will begin in July.
Earthworks in this area is on-going.
Utilities- Pembina and ATCO Pipeline relocation work is on-going in this area.

Mainline Anthony Henday Drive (Between Yellowhead Trail and Sherwood Park Freeway)
Detour work is on-going in this area.
In preparation for the traffic shift onto the southbound lanes of Anthony Henday Drive.

North Saskatchewan River (Road Segment 2 - Site 20)
Flood damage repair work has commenced.
Substructure work is on-going (columns and pier abutment).
Earthworks in this area is on-going.

130 Ave Area (Road Segment 2 - Site 21)
Substructure work is active at the Pier.
MSE Wall construction is on-going.
Roadwork is on-going in this area.

Hayter Road / CN Railroad Yard Area (Road Segment 3 - Site 22)
Road fill is on-going for the new Meridian Street.
Preparation work has begun for MSE Wall construction.
Utilities- Pembina Pipeline relocation work is on-going.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3 - Site 23 & 24)
Substructure work is active at these sites.
Ground preparation for MSE Wall construction is on-going.
Pond work is on-going in this area.
Waterline relocation work is on-going in this area.

Anthony Henday Drive & CN Railroad (Road Segment 3 - Site 26)
Abutment fills and Pond work is on-going in this area.

Baseline Road and Anthony Henday Drive (Road Segment 4 - Site 28)
Demolition of existing eastbound bridge is complete, with new traffic patterns in place.
Substructure work is on-going in this area.
Preparation for Pile Driving work has commenced.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drive Area (Road Segment 4 - Site 29)
Demolition of existing westbound Sherwood Park Freeway Bridge is complete, with new traffic patterns in place.
Demolition of 76 Ave Bridge is complete, with new traffic patterns in place.
Substructure work is on-going in this area.
Storm sewer work is on-going in this area.

Sherwood Park Freeway and 17th Street (Road Segment 4 - Site 30)
Bridge culvert work has commenced in this area.

Sherwood Drive & Yellowhead Trail (Road Segment 5 - Site 32)
Sanitary-line relocation work has commenced.
Drainage work is on-going in this area.

Off Site
Concrete girders are being fabricated.
Steel girders are being fabricated.
MSE Wall panels are being fabricated.
Bridge bearings are being fabricated.

May 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Bridge 15.7 girder erection will start late June.
Other bridge components are under fabrication (bearings and bracings)
Drainage and Earthworks have recommenced in this area.
Site 16-MSE Wall construction will be completed in June.

CN Railroad Area (Road Segment 1-Site 17)
Preparing the ground for MSE Wall construction.
MSE Wall construction is to begin in June.

18th Street/ LRT Area (Road Segment 1- Site 18)
Utilities- Pembina Line relocation work is on-going.
Pile Driving is to commence in June.

153rd Ave Area (Road Segment 1-Site 19)
Substructure work is on-going, currently focusing on the abutment construction.
MSE Wall construction will be wrapping-up in June.
Earthworks in this area has recommenced.

North Saskatchewan River (Road Segment 2-Site 20)
Steel girder fabrication is on-going.
Substructure work is on-going (columns and pier abutment)
Earthworks in this area has recommenced.

130 Ave Area (Road Segment 2-Site 21)
Substructure work is active at the Pier.
MSE Wall construction will commence in June.

Hayter Road / CN Railroad Yard Area (Road Segment 3-Site 22)
Substructure wok is active at the Pier.
Road fill is on-going for the new Meridian St.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3-Site 23 & 24)
Pile Driving is continuing.
Substructure work is active at the site.
Ground preparation for MSE Wall construction is on-going.
Pond work has commenced in this area.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
Demolition of existing eastbound bridge is complete, with new traffic patterns in place.
Substructure work is on-going in this area.
Detour work is on-going.

Wye Road, Sherwood Park Freeway, & Anthony Henday Drive Area (Road Segment 4-Site 29)
Detour work is on-going in this area.
Westbound bridge demolition on Sherwood Park Freeway is scheduled to occur mid-June.
Substructure work is on-going in this area.
Drainage work is on-going in this area.

Sherwood Drive & Yellowhead Trail (Road Segment 5- Site 32)
Earthworks is on-going in this area.
Sanitary-line relocation work is scheduled to occur mid-June.
Drainage work is on-going in this area.

Off Site
Concrete girders are being fabricated.
Steel girders are being fabricated.
MSE Wall panels are being fabricated.
Bridge bearings are being fabricated.

 

April 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Site 15- Substructure work is on-going, including columns, and is nearly complete.
Bridge 15.7 girder erection will start in the beginning of May.
Other bridge components are under fabrication (bearings, bracings, and girders).
Site 16- MSE Wall construction is starting back up.

153rd Ave Area (Road Segment 1-Site 19)
Substructure work is on-going, currently focusing on the pier cap construction.
MSE Wall construction is commencing.
Utilities- Pembina pipeline work is active.

North Saskatchewan River (Road Segment 2-Site 20)
Pier foundation construction is almost complete for the active pier.
Substructure work has begun (columns)

130 Ave Area (Road Segment 2- Site 21)
Substructure work is wrapping up and will be starting on the deck soffit.
MSE Wall construction is commencing again.
Pond work has started.
Utilities- Pembina pipeline work is active.

Hayter Road / CN Railroad Yard Area (Road Segment 3-Site 22)
Road fill is on-going for the new Meridian St.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3- Site 23 & 24)
Pile Driving is continuing (Bridge 23.2, 23.5, and 24.3)
Straddle Bent is being built in Site 24.5.
MSE Wall construction is starting (Bridge 23.7)

Anthony Henday Drive and CN Railroad Area (Road Segment 3-Site 26)
Pond Work has commenced.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
Substructure work is on-going, in the median of Anthony Henday Drive.
Detour work is starting.

Wye Road and Anthony Henday Drive (Road Segment 4-Site 29)
Substructure work has commenced.
Pond work has commenced.

Off Site
Concrete girders are being fabricated.
Steel girders are being fabricated.
MSE Wall panels are being fabricated.
Bridge bearings are being fabricated.

March 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 &16)
Pile Driving is complete.
Pier cap construction on-going- Bridge 15.5 & 15.7
Substructure work is on-going (mostly complete). Pile-cap and Pier-cap construction is complete. Abutment construction is 80% complete.
Girder fabrication is complete for Bridge 15.7. Birders will be erected next month
A water-line is being relocated in Site 16.
Other bridge components are under fabrication (bearings and bracings)

18 ST/ LRT (Road Segment 1-Site 18)
Pile Driving is 65% complete.

153rd Ave Area (Road Segment 1-Site 19)
Substructure work is on-going.
Columns are ow being poured.
Pier-cap construction is underway.

North Saskatchewan River (Road Segment 2-Site 20)
Pile Driving is complete at the south abutment
Pier foundation construction has begun.
Pond outfall is constructed & associated storm-line instillation has begun.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3- Site 23 & 24)
Pile Driving is continuing (Bridge 24.3 & 24.4) (40% complete).
Straddelbend substructure is being built in Site 24.5.
Pile Driving has commenced in Bridge Site 23.3/23.5 (for the curved flayover ramps)
Relocation of electrical work is underway in support of sprong MSE wall work.

Monster Manhole (Road Segment 3-Site 24)
Excavation and shoring is complete,
This will be followed by backfill placement and shallow pipe work.
Bypass pipework is active.
Temporary works is underway.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
Pile Driving is complete.
Substructure work has commenced, is the median of the Anthony Henday.

Wye Road and Anthony Henday Drive (Road Segment 4-Site 29)
Pile Driving is nearly complete.
Instillation of culverts is on-going.

Sherwood Park Freeway / 17th Street (Road Segment 4-Site 30)
Pile Driving will commence next month.

Utilities-Project wide pipeline and utility relocations are underway.

Off Site
Concrete girders are being constructed for bridges.
Steel Girder construction.
MSE Wall panels are being constructed.
Bridge bearings are being constructed.

 

February 2013

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15 & 16)
Pile Driving is complete.
Pier cap construction-Bridge 15.5 and 15.7
Substructure work is on-going. This includes Pile-cap, Pier-cap, and Abutment construction (majority is complete).
Girder fabrication is complete for Bridge 15.7. Girders will be erected next month.
A water-line is being relocated in Site 16.

18 St/ LRT (Road Segment 1-Site18)
Pile Driving will commence.

153rd Ave Area (Road Segment 1-Site 19)
Substructure work is on-going.
Columns are now being poured.

North Saskatchewan River (Road Segment 2-Site 20)
Pile Driving has commenced.
Sheet Pile Driving has commenced in order to do substructure work.
Pond outfall is being built.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3-Site 23 & 24)
Pile Driving is continuing (Bridge 24.3 & 24.4)
Straddelbend substructure is being built in Site 24
Pile Driving has commenced in Site 23.

Monster Manhole (Road Segment 3-Site 24)
Excavating deep into the earth.
Bypass instillation is complete.
Temporary works is underway.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
Pile Driving is mostly complete.
Substructure work has commenced.

Wye Road and Anthony Henday Drive (Road Segment 4-Site 29)
Pile Driving is on-going.
Instillation of culverts.

Utilities- Project wide pipeline and utility relocations are underway.

Off Site
Concrete girders are being constructed for bridges.
Steel Girder construction.
MSE wall panels are being constructed.
Bridge bearings are being constructed.

 

December 2012/January 2013

All MSE wall construction is in hibernation for the winter.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Pile Driving is complete.
Pier Cap construction - Bridge 15.5 and 15.7.
Substructure work is on-going. This includes Pile-Cap, Pier-Cap, and Abutment construction.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 16)
Pile Driving is complete.

18th Street and 153rd Avenue area (Road Segment 3-Site 23 & 24)
Pile Driving is continuing (Bridge 24.3 & 24.4)

Monster Manhole (Road Segment 3-Site 24)
Excavating deep into the earth.
Bypass line instillation is complete.
Temporary works is underway.

Baseline Road and Anthony Henday Drive (Road Segment 4-Site 28)
Pile driving is mostly complete.

Wye Road and Anthony Henday Drive (Road Segment 4-Site 29)
Pile Driving will commence.
Instillation of culverts.

Utilities- Project wide pipeline and utility relocations are underway.

Off Site
Concrete gurters are being constructed for bridges.
Steel gurter construction will begin shortly.
MSE wall panels are being constructed.

November 2012

All MSE wall construction is in hibernation for the winter.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
Pile Driving is continuing.
Substructure work is on-going. This includes Pile-Cap, Column, Pier-Cap, and Abutment construction.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 16)
Pile driving is completed for the time being.

Saskatchewan River Crossing (Road Segment 2-Site 20)
Drill shaft construction has commenced.
Foundation work for the piers on the river has commenced.

Northside- excavating materials down to roadway grade.
Southside-almost done filling earthwork filling to roadway grade.

Yellowhead Trail and Anthony Henday Drive (Road Segment 3-Site 23)
Pile driving will commence in December.

Monster Manhole (Road Segment 3-Site 24)
Excavating deep into the earth.
Installing bypass line to cast connection block.

Wye Road and Anthony Henday Drive (Road Segment 4-Site 29)
Pond Excavation

October 2012

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
MSE/ Panel erection is ongoing.
Substructure work continuing


Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 16)

MSE work has begun.
Pile Driving is continuing

Saskatchewan River Crossing (Road Segment 2- Site 20)
Berm construction is complete.
Earthwork/Roadwork activities, north and south of the river, is ongoing.
Slope stability piles are being installed on the north side of the river.

130 Ave (Road Segment 2-Site 21)
Common haul, grading, earthworks is ongoing.
Clearing, grubbing and stripping is complete.

Yellowhead Trail/Canadian Pacific Railroad (Road Segment 3-Site 24)
Clearing, grubbing, and stripping is complete.
MSE wall foundation work has begun.

Yellowhead Trail/Broadmor Blvd/Sherwood Drive (Road Segment 3&5-Site 25&32)
Clearing, grubbing, and stripping is ongoing.

Sherwood Park Freewar (Road Segment 4-Site 29)
Sleeving and MSE work has commenced.
Clearing, grubbing, and stripping is ongoing.

Crews are installing culverts project-wide.
Utility relocates are progressing project wide.

September 2012

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 15)
MSE work progressing.
Panel erection has begun.
Substructure work has commenced.

Manning and Anthony Henday Drive Interchange (Road Segment 1-Site 16)
Pile driving has commenced.
Clearing, grubbing, and stripping is ongoing

Saskatchewan River Crossing (Road Segment 2-Site 20)
Berm construction has started, in order to prepare for the pier foundation work.
Clearing, grubbing, and stripping is ongoing (continues south to Site 22)

130 Ave (Road Segment 2-Site 21)
Common haul grading earthworks is progressing.
Clearing, grubbing, and stripping is ongoing.

Yellowhead Trail/Canadian Pacific Railroad (Road Segment 3-Site 24)
Pile Driving has commenced.
Clearing, grubbing, and stripping is ongoing.

Yellowhead Trail/Broadmor Blvd/Sherwood Drive (Road Segment 3&5-Site 25&32)
Clearing, grubbing, and stripping is ongoing.

Sherwood Park Freeway (Road Segment 4- Site 29)
Demolition work completed.
Clearing, grubbing and stripping has commenced.

Crews are installing culverts project-wide.

August 2012

Manning and Anthony Henday Drive interchange (Road Segment 1 - Site 15)
MSE wall foundation work and pile driving is ongoing.
MSE work progressing, panel erection will be starting this month.

Manning and Anthony Henday Drive interchange (Road Segment 1 - Site 15) and Saskatchewan River Crossing (Road Segment 2)
Clearing, grubbing, and stripping is ongoing.

Saskatchewan River Crossing (Road Segment 2)
Crews are finished building an access road to river bridge site.
Clearing, grubbing, and stripping is ongoing

Crews are installing culverts project-wide.

July 2012


Manning and Anthony Henday Drive interchange (Road Segment 1 - Site 15)
MSE wall foundation work and pile driving is ongoing.

Manning and Anthony Henday Drive interchange (Road Segment 1 - Site 15) and Saskatchewan River Crossing (Road Segment 2)
Clearing, grubbing, and stripping is ongoing.

Saskatchewan River Crossing (Road Segment 2)
Crews are finished building an access road to river bridge site.

Clearing, grubbing, and stripping is ongoing.

 

June 2012

Manning and Anthony Henday Drive interchange (Road Segment 1 - Site 15)
Construction crews are constructing the bridge foundations and retaining walls. Specifically, they are stripping the topsoil, preparing to construct the mechanically-stabilized embankment (MSE) walls and preparing for pile driving operations. 

Saskatchewan River Crossing (Road Segment 2 - Site 20)
Crews are stripping topsoil and building a temporary access road on the north side.

North of Hayter Rd. to the south side of the North Saskatchewan River (Road Segment 3 - Sites 20 to 22)
Crews are clearing and grubbing in preparation for construction.

Wye Road (Road Segment 4 - Site 29)
Crews are clearing and grubbing. They will also demolish some abandoned homes.